Trimline carried out significant work in the Colonnade restaurant, including the installation of new stone counters in the buffet area, cold counter, show galley plus tiling/flooring and electrical work. New stone waterfall tops were also installed on a number of tables in the restaurant area. The work was carried out during repositioning of the ship from Asia to Europe.
Other work on this vessel included...
35
People
People
33
Days
Days
611
Products
Products
2778
Tasks
Tasks
7986
Hrs Work
Hrs Work
£500k - 1M
Value
Value